Ashghal remotely opens the last interchange on Al Khor Road project

Published: 25 Mar 2020 - 03:30 pm | Last Updated: 01 Nov 2021 - 10:17 pm
Peninsula

The Peninsula

Ashghal and Qatari Diar Company opened a new interchange connecting Al Khor Road and Al Ramth Road - linking north and central Lusail - using remote communication technology.

On this occasion, Yousef Al-Emadi, Projects Affairs Director, stressed that Ashghal seeks to provide alternative and unconventional solutions for project management in the face of coronavirus (Covid 19), adding that the authority has taken the necessary precautions to confront Corona Virus, especially in the workplace.

The new junction is the last one on the Al Khor Road project, which is 97% complete, and will be fully ready by mid-2020, as cycling and walking tracks and other service roads are still under construction.

The new 2.4-km Al Khor Road interchange, built by Ashghal, is a major link, as it integrates with the new ‘Jo Al Ramth’ Road constructed by Qatari Diar helping those coming from the heart of Lusail to reach Al Khor Road via the new interchange.

The new interchange is a key feeder connecting Lusail Stadium on one side and Lusail Station on the other side and serving Lusail North via the new road in the east and Rawdhat Al Hamama, Al Kheesa and Wadi Al Banat in the west.

The interchange consists of four bridges, two exit loops, and four exits, along with four underpasses. The interchange will improve traffic in the area, as it provides a free traffic flow to 28,000 vehicles per hour.

The remote opening was done in the presence of Engineer Yousef Al-Emadi, Projects Affairs  Director,in Ashghal, Engineer Fahad Al Jahrami, Head of Project Delivery Sector – Qatar, Engineer Bader Al Darwish, Manager of Highway Projects Department, Brigadier Mohamed Marafi, Director of Traffic Engineering and Safety Department at the General Directorate of Traffic, Mr. Mishaal Al Nuaimi, and Mr Ali bin Fahad Al Shahwani, Members of the Municipal Council, and a number of officials and engineers of Ashghal and Qatari Diar.“

Jo Al Ramth” road

The new road extends 2.4 km from the new interchange on the Al Khor Road to the central part of Lusail City, which helps access Lusail City districts namely, Fox Hills, Lusail Plaza, Al Kharaej, Golf District, and the Qetaifan Islands. The road corridor includes tunnels and underpass with a length of 260 meters along with Walkways and Bike Lanes of 4.2 km. The road includes 160 trees, shrubs and palm trees, and 36,280 square meters of ground covers, green spaces and open spaces of 50,000 square meters, as well as a 5-km storm water drainage. In addition to artwork along the road for a distance of 850 meters, to be completed by the end of the year 2020.

Al Khor Road

Al Khor Road main carriageway serves as an alternative route to Al Shamal Road and a major link between the northeast of the country and Doha, where the new road will shorten travel time taken by road users coming from Al Khor up to 65%, especially as the new road accommodates about 20000 vehicle per hour in both directions, where it consists of five lanes in each direction instead of two lanes in each direction.  Old Al Khor Road  used to accommodate 8000 vehicles per hour. 

Olympic Cycling Track 

The Olympic Cycling Track extends along 33 km and a width of seven meters that will enable international sports competitions, especially since the Olympic path is designed to allow speeds up to 50 km per hour, notably with the construction of 29 tunnels and 5 bridges. Ashghal has provided a five car parking area stretching along the path near Qatar University, Lusail Station, Lusail International Circuit, Semaisma Interchange and Al Bayt Stadium, and the authority installed 1,450 lighting poles dedicated to the vital path to encourage cycling at night.

Residential Areas

Al Khor Road along with Al Khor serves more than 20 residential areas such as Semaisma, Umm Qarn, Tinbak, Wadi Al Banat, Rawdat Al Hamama, Legtaifiya, Lusail, the Pearl and Al Turfa.

The new road also facilitates access to Mesaieed and Dukhan through its intersection with Al Majd Road.

Facts and Figures

Upgrading works on Al Khor Road started in the last quarter of 2016 to reach 97% of progress. Upon project completion in mid-2020, a great deal of road preparation works will have been done comprising of 11.5 million cubic metres of filling and compacting works, 2.3 million tonnes of asphalting and 580 thousand cubic metres of concrete. In addition to implementing excavation works comprising of 10.87 million cubic metres, 167 km of rainwater and sewage water drainage lines and 110 km to extend the pipeline for irrigation and treated water treatment network along with 160 km of electricity and 290 km of telecommunications network.