Simplifying the procedures further to save time and efforts of service users, the Ministry of Municipality and Environment (MME) has upgraded electronic system for the issuance of building permits, certificates of completion of construction of building among other services.
The new amendments which will come into effect from February 1, 2020 have merged the procedures of obtaining permit for placing board at construction sites within building permit in a single application, said the Ministry of Municipality and Environment in a statement.
Inspection from Qatar General Electricity and Water Corporation (Kahramaa) at the completion of the building for warehouses will no more be needed in the new system. The new amendments aim at unifying the performance evaluation indicators of all service agencies so that they do not exceed 10 days for all types of projects.
The new system was developed by the MME in coordination and cooperation with the General Directorate of Civil Defense at the Ministry of Interior; Kahramaa and the Public Works Authority (Ashghal).
The Ministry explained that the new amendments include making the procedure of applying for site board, a part of the building permit, so that the consultancy firm, the designer or owner, submits one application for a building permit. The procedure for obtaining a site board license was a separate requirement from the licensee or contractor to display the details about the project as per the existing system.
The amendments also include the incorporation of the survey report issuance procedure, knowing that this report aims at place markings for indicating the boundaries of the land for which a license or building completion certificate will be issued.
The new amendments included obtaining the survey report by submitting the application through the website. It is issued through the system for each new license or building completion certificate, and the cost of the survey report is also included in the building permit fees or building completion certificate.
The new amendments will abolish the inspection by Kahramaa, at the stage of completion of construction for warehouses only, which was used to be mandatory for issuing construction completion certificate and to get service connection.
The amendments also include the inclusion of payment of fees for the delivery of services of Kahramaa in the first invoice for warehouses only. The amendments also include incorporating the application for connection to sewage network into the building permits system. The amendments also included the abolition of the inspection of telecommunications service providers at the stage of building completion. The construction completion fee payment procedure has also been incorporated into the procedures for requesting a construction completion certificate.
MME launched the electronic system for building licenses on February 10, 2014 to be inclusive of all transactions and procedures required by the construction. The system includes all relevant authorities and required approval in the State to finish the issuance of the building permit.
The electronic system works to transfer the transactions to all parties involved in the process of issuing building permits.